Dec 21 2022

December construction update

Posted by Coastal GasLink

Finishing 2022 at more than 80% completion, Coastal GasLink sets a strong foundation for final year of construction

2022 was an incredible year filled with many construction milestones, as the project achieved more than 80 per cent completion. Some of the most notable achievements include the 100% pipe install in Sections 1 and 4, the completion of our Wilde Lake compressor station and the commencement of pipe install at Cable Crane Hill – which has reached 45 per cent pipe install ahead of schedule. This year, we also safely and successfully completed 9 out of 10 major watercourse crossings.

To date, our team has installed nearly 490 km of pipe across the 670-kilometer route, and steady progress is made each day. Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak.

Read our full December construction update.